On 16 November 2016, the District Court of Limburg ("District Court") rendered a final judgment in the Dutch prestressing steel case (ECLI:NL:RBLIM:2016:9897).

The District Court ruled that the damages claims are time-barred under German law and therefore dismissed all claims against the defendant prestressing steel producers who appeared in the proceedings and filed defences including, inter alia, a defence of statutory limitation. However, the claims were granted in their entirety against two defendants who failed to appear in the proceedings.

In 2010, the European Commission fined 17 producers of prestressing steel for having infringed European competition law by participating in a price-fixing and market-sharing cartel. On 31 December 2013, several entities of the Deutsche Bahn group of companies brought civil proceedings in the District Court of Limburg, the Netherlands. They claimed that the defendant producers are jointly and severally liable for all loss suffered due to the infringement. In a judgment of 25 February 2015 (ECLI:NL:RBLIM:2015:1791) the Court accepted jurisdiction to rule on damages claims against all alleged cartel participants, as a Dutch 'anchor' was amongst the defendants (see our April 2015 Competition Law Newsletter). After that judgment, the defendants filed several additional defences.

According to defendant DWK Drahtwerk Köln GmbH ("DWK"), the Court should have stayed the proceedings and subsequently declared the writ of summons void as it had not been correctly served upon DWK. Referring to European case law, the Court reiterated that the national procedural rules of the competent court must be applied, i.e. in this case: the Dutch rules of civil procedure. The Court ruled that as DWK voluntarily appeared in the proceedings and DWK's interests were not unreasonably prejudiced, the nullity of the writ of summons was 'healed' when DWK appeared before the Court.

The Court then turned to the defence of statutory limitation, which had been invoked by all defendants who appeared in the proceedings. Pursuant to Article 7 of the Act regarding Conflict of Laws on Torts (Wet conflictenrecht onrechtmatige daad), the rules of the law applicable – in this case: German law – determine the limitation periods for damages claims as well as the interruption and the suspension thereof. Under German law, a long-stop limitation period of 10 years and a short-stop period of 3 years apply. The defendants argued – and Deutsche Bahn did not dispute – that the long-stop period started to run no later than September 2002. Therefore, in the absence of a valid act of interruption or suspension, Deutsche Bahn was out of time when it issued the proceedings on 31 December 2013.

Referring to Article 33(5) of the German Competition Act (Gesetz gegen Wettbewerbbeschränkungen, hereinafter "GWB") that came into force in July 2005, Deutsche Bahn argued that the limitation period had been suspended by operation of law for the duration of the European Commission's investigation into the competition law infringement. However, the Court sided with the defendants and held that, in the absence of specific transitional provisions, Article 33(5) GWB could not be applied retroactively to damages claims in relation to loss suffered prior to July 2005. The Court acknowledged and discussed a 2014 judgment of the Higher Regional Court of Düsseldorf, in which a German appeal court had applied Article 33(5) GWB retroactively, but did not find that court's reasoning persuasive. At first blush, it may seem remarkable that a Dutch court of first instance would disagree with a German appeal court on the proper application of a provision in the German Civil Code. The retroactive application of Article 33(5) GWB by the Higher Regional Court of Düsseldorf is, however, subject to significant controversy. See for a recent decision in which another German appeal court ruled that Article 33(5) GWB cannot be applied retroactively the Higher Regional Court of Karlsruhe, 9 November 2016, 6 U 204/15 Kart (2), with further references to case law and literature on the issue.

In the alternative, Deutsche Bahn relied on the European Court of Justice judgment in the case of Manfredi (ECLI:EU:C:2006:461), arguing that a strict interpretation of the (old) German rules on statutory limitation would run afoul of the principle of effectiveness. Again, the Court disagreed. In its Manfredi decision, the highest European court had pointed out that a limitation period that begins to run before the claimant has knowledge of the infringement could make it practically impossible to seek compensation, "particularly if that national rule also imposes a short limitation period which is not capable of being suspended". However, as the defendants had argued and the Court accepted, the German long-stop limitation period of 10 years was neither short, nor incapable of being suspended. Therefore, the Court concluded that Deutsche Bahn's damages claims were time-barred.

Still, for Deutsche Bahn the case did not result in a full dismissal of its claims. As a matter of Dutch civil procedure, courts cannot apply rules of statutory limitation ex officio. The claims against the two defendants who did not appear in the proceedings and omitted to put forward a defence, were subjected only to a prima facie review of their merits. As these claims appeared to be neither unlawful nor unfounded, the claims were granted in their entirety. The Court ruled that these defendants infringed Article 101 TFEU and are jointly and severally liable for all the loss suffered by Deutsche Bahn as a result of the infringement.

Related news

11.04.2019 NL law
Double roles in attributing knowledge

Short Reads - The knowledge of a person who in fact runs a company can be attributed to the company if the sole director and shareholder is a 'straw man', the Supreme Court confirmed in a judgment of 29 March 2019. The rules by the Supreme Court are not revolutionary or even new. But circumstances essential for the attribution of knowledge are ignored. The double role played by the 'man in charge' raises questions about how to apply the rules as identified by the Supreme Court to the facts

Read more

28.03.2019 NL law
European Parliament votes in favour of representative actions for consumers

Short Reads - On 26 March 2019 the European Parliament approved an amended version of the European Commission's proposal for a Directive on representative actions for the protection of collective interests of consumers, following a debate on 25 March 2019. The Directive will become law once the Council and the European Parliament reach an agreement on the European Commission's proposal. The Council has not yet been able to adopt a position on the Directive, meaning that the Directive will most likely be considered again after the ­­­European elections in May 2019 by a different European Parliament

Read more

10.04.2019 NL law
Damage due to a defective driveway and the Dutch twenty year limitation period: When does limitation start in case of a continuous event that causes damage?

Short Reads - On 22 March 2019, the Dutch Supreme Court ruled (ECLI:NL:HR:2019:412) that the strict liability for buildings (opstalaansprakelijkheid) is not linked to a specific damaging act but to a damaging condition, as referred to in section 6:174 DCC. Therefore, there is no reason to regard a damaging act as an 'event that caused damage' as referred to in section 3:310 DCC concerning the limitation period for claims for damages.

Read more

04.04.2019 NL law
European Court of Justice: actio pauliana is covered by jurisdiction rule of forum of contract. A judgment with foreseeable consequences?

Short Reads - Imagine that a debtor voluntarily concludes a transaction with a third party where he knows (or should know) that it hinders the creditor's possibilities of collecting the debt. In civil law countries, a creditor can invoke the nullification of that legal act by means of a so-called actio pauliana. This raises the question of which court has jurisdiction in the case of an international dispute, regarding an actio pauliana, that is instituted by a creditor against a third party?

Read more

Our website uses functional cookies for the functioning of the website and analytic cookies that enable us to generate aggregated visitor data. We also use other cookies, such as third party tracking cookies - please indicate whether you agree to the use of these other cookies:

Privacy – en cookieverklaring