Flemish Government approves Technical Regulations Distribution Gas and Electricity

Flemish Government approves Technical Regulations Distribution Gas and Electricity

Flemish Government approves Technical Regulations Distribution Gas and Electricity

19.11.2012 BE law

Novelties in the VREG’s amended Technical Regulations Distribution Gas and Electricity concern closed distribution grids, congestion management, flexible connections, and the injection ofbiomethane in the natural gas distribution grid. The Flemish Orders approving these Regulations were recently published in the Official Journal. However, one could question the competence of the Flemish Government in approving these Regulations.

On 15 May 2012 the VREG, the Flemish Energy Market Regulator, adopted new Technical Regulations for the Distribution of Gas and Electricity1. The Flemish Government approved these regulations by issuing two orders, which were published recently in the Official Journal2.

The Technical Regulations were amended to further implement the third Energy Package. The terminology used in these Regulations also conformed to that of the Energy Decree.

The most significant amendments concern:

1. Closed Distribution Grids

The Energy Decree covers the construction and exploitation of closed distribution grids (chapter VI). The Technical Regulations supplement these provisions with technical prescriptions. According to these prescriptions, operators of closed distribution grids enjoy certain freedom when they lay down for example, procedures, terms in model contracts and forms for the operation of the closed distribution grids. However, these documents should be disclosed, e.g., to the ARP or the VREG, whenever these authorities request for them (Art. I.6.1.4). Furthermore, the concerning DSO will remain competent to adopt a Connection Regulation. 
The Technical Regulations also introduce two new notions: Downstream Access Point (Achterliggend Toegangspunt) and Coupling Points (‘Koppelpunten’)3
The first one, Downstream Access Point, is the access point for producers or consumers from the closed distribution grid. This notion was introduced so that it could be clearly distinguished from access points to public grids.  
The second notion, Coupling Points, refers to points where closed distribution grids and the public distribution grid are connected to each other. This notion is used to distinguish from Connection Points. According to the VREG the notion is inspired by the coupling models that exist among DSOs, or between a DSO and a TSO. Coupling Points would theoretically be the most pure term because closed distribution grids are rather a form of distribution grids a connected grid user4
However, the Technical Regulations specify clearly that installations behind different access points may not be connected to each other without explicit permission from the DSO (Art. III.5.1.3). Similarly, the Technical Regulation Distribution Electricity also prohibits installations from being produced behind different coupling points (Art. III.8.1.5).

2. Congestion Management

The Technical Regulation Distribution Electricity sets out a modified congestion management. All requests for connection and the corresponding capacity reservations should be treated in the order requested (first-come, first-served), but the electricity DSO should give priority to CHP or renewable energy installations (Art. III.3.3.24). Capacity reservations will only be valid for a period of 2 years. Capacity reservations are neither marketable nor transferable (Art. III.3.3.31). 

3. “Flexible connections” :

are also formalized, despite opposition by FEBEG, the Federation of Belgian Electricity and Gas Companies5. Flexible connections are connections for which the producer would agree not to inject electricity if, at anytime, the grid were to be saturated. The Technical Regulation Distribution Electricity states that the electricity DSO may decide to allow for an “abnormal” connection, depending on the characteristics of the local electricity distribution grid or if the installation of the grid user causes harmful interferences or excessive voltage fluctuations (Art. III.3.1.3). Furthermore, for projects with a global production capacity of 1000 kVA or more, or for projects where a temporary limitation of the production would be necessary in n-1 situations, the DSO may impose limitations on the production based on objective criteria, if exceptional exploitation circumstances require it and provided that these limitations have been embedded in a contract (art. III.4.4.2). 

4. Injection of Biomethane

Although no injection points currently exist on the distribution grid in Flanders, the Technical Regulation Distribution Gas allows for the possibility to inject biomethane in the natural gas distribution grids. The injection is, however, limited to the middle pressure grids of categories B and C. The operator of the coupled grid can demand that the biomethane fulfill certain conditions, e.g., regarding the composition of the gas.

Other amendments to the Technical Regulations concern improvements in certain processes and provisions regarding the introduction of smart metering.

However, it should be noted that the Flemish Government’s approval of the Technical Regulations might not conform with European law. According to Art. 41(6) of the third Gas Directive and Art. 37(6) of the third Electricity Directive, the regulator is competent for fixing or approving the terms and conditions for the connection and access to national networks and the provision of balancing services, for example. In the parliamentary preparations regarding the implementation of the third Energy Package at the federal level, the Council of State noted that a provision allowing the King to lay down the federal Technical Regulations would violate European legislation6. The Flemish Technical Regulations were drafted by the VREG and only approved by the Flemish Government, according to Art. 4.2.1 §3 of the Energy Decree. Nevertheless, one may wonder whether such approval, even without any amendments, conforms with European law, since such approval is not theoretically necessary for the Technical Regulations to enter into force.

Footnotes

 
  1. According to art. 4.2.1 of the Energy Decree 
  2. Order of the Flemish Government of 25 May 2012 regarding theapproval of the technical regulation distribution gas, Official Journal 14 November 2012; Order of the Flemish Governmentof 25 May 2012 regarding the approval of the technicalregulation distribution electricity, Official Journal 14 November 2012
  3. Cf. terminology of Art. 4.6.2 Energy Decree. 
  4. Cf. Parl. St. Vl. Parl. 2010-11, nr. 1147/1, pp. 39–40. 
  5. PowerPoint-presentation of FEBEG of 11 April 2012, “Congestion Management by distribution”.  FEBEG argued that flexible connections would discourage grid investments and investments in generation capacity, and that they constitute discrimination between existing and new connections. 
  6. Parl. St. Kamer 2011-12, nr. 1725/1, p. 281

All rights reserved. Care has been taken to ensure that the content of this e-bulletin is as accurate as possible. However the accuracy and completeness of the information in this e-bulletin, largely based upon third party sources, cannot be guaranteed. The materials contained in this e-bulletin have been prepared and provided by Stibbe for information purposes only. They do not constitute legal or other professional advice and readers should not act upon the information contained in this e-bulletin without consulting legal counsel. Consultation of this e-bulletin will not create an attorney-client relationship between Stibbe and the reader. The e-bulletin may be used only for personal use and all other uses are prohibited.

 

Team

Related news

05.10.2018 NL law
Presentaties seminar Dienstenrichtlijn en Detailhandel

Articles - Met het arrest van het Europese Hof van Justitie en de vervolguitspraak van de Afdeling bestuursrechtspraak van de Raad van State in de zaak Visser Vastgoed in Appingedam is vast komen te staan dat de Dienstenrichtlijn van toepassing is op bestemmingsplannen die detailhandel reguleren.

Read more

15.10.2018 BE law
Gestion et traçabilité des terres en Wallonie. Nouvel arrêté du gouvernement.

Articles - Dans la continuité de l'adoption, le 1er mars 2018, du décret relatif à la gestion et à l'assainissement des sols, le Gouvernement wallon a mis en place un certain nombre de mesures relatives à la gestion et à la traçabilité des terres en Wallonie. Ces mesures entreront en vigueur le 1er novembre 2019 (et partiellement le 1er septembre 2018).

Read more

04.10.2018 BE law
Nieuw tijdperk voor Vlaamse woonreserves aangebroken

Articles - De Vlaamse regering beoogt het wettelijk kader in de zogenaamde "woonresergebieden" (waaronder de woonuitbreidingsgebieden) grondig te wijzigen. Ofwel krijgen de gebieden de volwaardige status als woongebied, ofwel krijgen ze een andere bestemming dan wonen. De regeling laat toe om gemeenten voor een openruimtebestemming te laten kiezen. Hierna een overzicht van het voorstel van de Vlaamse regering en de reactie van de adviesraden op het voorstel.

Read more

Our website uses cookies: third party analytics cookies to best adapt our website to your needs & cookies to enable social media functionalities. For more information on the use of cookies, please check our Privacy and Cookie Policy. Please note that you can change your cookie opt-ins at any time via your browser settings.

Privacy – en cookieverklaring